The Three-Runway System: A Three-Phase Process

Planning Approval Implementation
  • Environmental Impact Assessment studies
  • Associated design details
  • Funding options
  • Environmental permit
  • Financial arrangement
  • Other statutory process requirements
  • Detailed designs
  • Land formation
  • Construction of related facilities
About 2 Years* About 1 Year* About 8 Years*
The initial phase of the three-runway system project is expected to be completed by 2023*

* Indicative timeline that is subject to change