The building of the third runway is divided into three phases: planning, approval and implementation.
In the planning phase, the Airport Authority (AA) will commission statutory Environmental Impact Assessment (EIA) studies and study funding options. A number of approvals from the Government is needed before actual project implementation – land formation and construction of related facilities – can begin. The entire project is estimated to take about 11 years before the three-runway system is commissioned in 2023.
The Three-Runway System: A Three-Phase Process
| Planning | Approval | Implementation |
|---|---|---|
|
|
|
| About 2 Years* | About 1 Year* | About 8 Years* |
| It will take at least three years before actual project implementation | ||
* Indicative timeline that is subject to change