The building of the third runway is divided into three phases: planning, approval and implementation.

In the planning phase, the Airport Authority (AA) will commission statutory Environmental Impact Assessment (EIA) studies and study funding options. A number of approvals from the Government is needed before actual project implementation – land formation and construction of related facilities – can begin. The entire project is estimated to take about 11 years before the three-runway system is commissioned in 2023.

The Three-Runway System: A Three-Phase Process

Planning Approval Implementation
  • EIA studies
  • Associated design details
  • Funding options
  • Environmental permit
  • Foreshore and seabed gazettal
  • Financial arrangement
  • Land formation
  • Detailed designs
  • Construction of related facilities
About 2 Years* About 1 Year* About 8 Years*
It will take at least three years before actual project implementation

* Indicative timeline that is subject to change