Special Announcement

Future Development

HKIA Master Plan 2030
HKIA Master Plan 2030

HKIA is one of the finest and busiest airports in the world. The airport not only connects Hong Kong with the world but also makes significant social and economic contributions to the city. To strengthen Hong Kong's competitiveness and meet growing aviation demand, HKIA needs to be further developed. Hence, the AA has put forward the Master Plan 2030 which outlines two options for future airport developments.


Air traffic demand forecast
Air traffic demand forecast

The first step of the master planning process for HKIA is to determine the long-term air traffic demand forecast up to 2030. Commissioned to undertake this task, IATA Consulting forecast air traffic demand to reach about 97 million passengers, 8.9 million tonnes of cargo and 602,000 flight movements per year by 2030.


Aviation industry economic contributions
Aviation industry economic contributions

As an international and regional aviation centre, HKIA is a critical infrastructure that supports Hong Kong's competitiveness as an international business, financial, tourism and logistics hub. The Master Plan 2030 has evaluated the potential economic benefits from further airport development under the two options.


Airport development options
Airport development options

To plan ahead for future demand growth and maintain Hong Kong's competitive edge, the AA developed the Master Plan 2030 and suggested two development options for HKIA - to upgrade the existing two-runway system or to develop HKIA into a three-runway system.


Runway capacity
Runway capacity

Like any other airports in the world, HKIA has its limitation, for example, runway capacity. The capacity is affected by numerous factors including flight safety regulations, airspace limitations and geographical constraints. The runway capacity of the present two-runway system is expected to reach its saturation point around 2020.


Aircraft noise mitigation
Aircraft noise mitigation

When preparing the Master Plan 2030, a preliminary environmental assessment was conducted to ensure that the recommended airport expansion layout under Option 2 should minimise environmental impact as far as possible. Potential noise impact of the three-runway system has been assessed in the Master Plan 2030 using Noise Exposure Forecast (NEF) contours. Preliminary projections indicate that NEF levels under a three-runway system would not differ significantly from the 1998 levels.


Land reclamation
Land reclamation

If HKIA was to be developed into a three-runway system, reclamation of about 650 hectares of land in the north of the airport island is needed. While about 40% of the proposed reclamation area falls upon an area of contaminated mud pits that are of lower marine ecology value, a method calls "Deep Cement Mixing" is recommended for the reclamation in this area to minimise disturbance to the contaminated mud.


Building a green airport
Building a green airport

The AA is committed to protecting the environment and ensuring the sustainable development of the airport. Adhering to the three main principles - Reduce, Reuse and Recycle, numerous green initiatives have been incorporated into many aspects of the airport from its design, construction and daily operations to future planning.


Airport enhancements for future growth
Airport enhancements for
future growth


HKIA constantly upgrades its facilities and capacity to meet future demands. In 2010, HKIA completed the HK$4.5 billion enhancement programme for the airfield and passenger terminal which began in 2006. HKIA has started the Phase I Development of Midfield, the only large-scale undeveloped area on the airport island. The HK$7 billion project includes the building of a passenger concourse with 20 aircraft stands, additional taxiways, and the extension of the Automatic People Mover to connect with the new midfield concourse.


Page: 1 | 2

Prior approval is required for using this video. Please contact us.